On June 20, 2024, The DILG LFP Team, alongside the Dipaculao Municipal Project Monitoring Committee, conducted a site inspection of the ongoing Drainage System funded under the FY 2023 Seal of Good Local Governance Incentive Fund, and the Multi-Purpose Building (Evacuation Center) funded under the FY 2023 Local Government Support Fund - Financial Assistance to Local Government Units.
During the inspection of the Construction of the drainage system in Brgy. North Poblacion, the LFP team validated the 72.74% accomplishment as of June 18, 2024. This project is in line with the LGU's goals for more resilient and climate change adapative communities.
The inspection committee also visited the Multi Purpose Building (Evacuation Center) in Brgy. Borlongan, Dipaculao which has a current status of 95.83%. This was the pre-final inspection to observe any issues and ensure accuracy of the reported progress in the submitted documentary requirements.
Those in attendance were the following:
MLGOO Hannah Dizon
Engr. Rosanna C. Hernandez
Engr. Kenny Jean O. Nakar
Judy Abel- accounting office rep, JO
Dominador Aban- MBO
Ellynor Ignacio, King Albert Villanueva - MEO Staff
Fritz Naraja - mayor’s office staff/property custodian
Vivian Nidoy - admin aide iv/mpdo staff
Mark Anthony Canasa - mpdc
Darius Asgar -driver