On June 20, 2024, The DILG LFP Team, alongside the Dipaculao Municipal Project Monitoring Committee, conducted a site inspection of the ongoing Drainage System funded under the FY 2023 Seal of Good Local Governance Incentive Fund, and the Multi-Purpose Building (Evacuation Center) funded under the FY 2023 Local Government Support Fund - Financial Assistance to Local Government Units.

IMG 5581During the inspection of the Construction of the drainage system in Brgy. North Poblacion, the LFP team validated the 72.74% accomplishment as of June 18, 2024. This project is in line with the LGU's goals for more resilient and climate change adapative communities.IMG 5672 1

The inspection committee also visited the Multi Purpose Building (Evacuation Center) in Brgy. Borlongan, Dipaculao which has a current status of 95.83%. This was the pre-final inspection to observe any issues and ensure accuracy of the reported progress in the submitted documentary requirements.

Those in attendance were the following: 

MLGOO Hannah Dizon
Engr. Rosanna C. Hernandez
Engr. Kenny Jean O. Nakar
Judy Abel- accounting office rep, JO
Dominador Aban- MBO
Ellynor Ignacio, King Albert Villanueva - MEO Staff
Fritz Naraja - mayor’s office staff/property custodian
Vivian Nidoy - admin aide iv/mpdo staff
Mark Anthony Canasa - mpdc
Darius Asgar -driver

 PD CORNER EPC 2023